City of South Bend's First Street

6-W-972(011)-1

6-W-972(011)-1
First Street

A St to C St

FY 2025 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $578,240

County: Pacific   |   Legislative District: 19   |   Project Length: 0.14   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 04/10/2025

Project Information

Lead Agency SOUTH BEND
Funding Year 2025
Program SCAP
Current Phase Construction
Legislative District 19
Congressional District 3
Federal Route Number 9999
Project Length 0.14 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Dennis Houk
Contact Email dennis.houk@southbend-wa.gov
TIB Engineer Chris Langhoff
Last Payment Date 04/10/2025
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date   01/22/2025
Predesign Approval
Design Approval 12/15/2023 12/06/2023
Bid Auth. Approval 03/30/2025 02/25/2025
Construction Approval 04/30/2025 03/25/2025
Project Closeout 12/15/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 63,068 76,387
Right of Way 0 0
Total Design 63,068 76,387
     
Construction Engineering 63,068 66,387
Construction Contract 420,451 481,500
Other Construction 0 0
Total Construction 483,519 547,887
     
Funding Increase 31,653  
Total TIB Funding 578,240 624,274

Local Funding Partners

Funding Amount Percent
SOUTH BEND 46,034 7.4%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 46,034 7.4%

Project Description

Construct a new roadway with improved storm system between A Street and C Street. Existing concrete panels will be removed for the construction of new pavement section (HMA over crushed rock). Curb and gutter will be installed on both sides of the roadway for safety, and for storm runoff collection.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.