4th Street between Cedar Avenue Highland Avenue has only sidewalk on one side of the street. In addition, the street is not wide enough to allow bikes for students to travel to and from the Elementary, Middle School and High School. 4th Street is the only way to cross Brezee Creek for citizens driving, biking or walking from the east side of La Center to downtown businesses.
Projects — TIB Project Information
TIB Project Information
City of La Center's 4th Street
6-W-949(006)-1
6-W-949(006)-1
4th Street
Cedar Ave to Highland Rd
FY 2026 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $500,000
County: Clark | Legislative District: 20 | Project Length: 0.36 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | LA CENTER |
Funding Year | 2026 |
Program | SCAP |
Current Phase | Design |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | J069 |
Project Length | 0.36 mi. |
ADT | 2,897 |
Functional Class | Collector |
Type of Work | Reconstruction |
Project Contact | Tony Cooper |
Contact Email | acooper@ci.lacenter.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 01/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 10/15/2020 | 12/04/2024 |
Bid Auth. Approval | 06/01/2025 | |
Construction Approval | 07/01/2025 | |
Project Closeout | 09/30/2027 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 1,151,551 |
Construction Contract | 500,000 | 10,733,249 |
Other Construction | 0 | 0 |
Total Construction | 500,000 | 11,884,800 |
Total TIB Funding | 500,000 | 11,884,800 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LA CENTER | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
STBG Rural Federal Funds | 2,000,000 | 16.8% |
State Appropriation RCO regulated | 958,800 | 8.1% |
Protect Grant WSDOT | 8,426,000 | 70.9% |
Total Local Funding | 11,384,800 | 95.8% |
Project Description
The 4th Street widening project will provide 7-feet wide sidewalks on each side of the street, and 5-feet wide buffered bike lanes on each side. Retaining walls will be installed to facilitate the new sidewalk and bike lanes on each side. A new bridge will be placed over 4th Street to replace the undersized 36-inch culvert. This new bridge will connect travel lanes, the new sidewalk and the new bike lanes east and west of Brezee Creek
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Restores structural condition;
- Removes ADA barriers
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |