1st Street is the primary connection between Highway 2 and the communities north of May Creek. As such, it experiences significant traffic and is experiencing deterioration of the existing road surface. Given that the alternative means of accessing these neighborhoods is unweildly and difficult, it is in the communities interest to maintain a safe primary access.
Projects — TIB Project Information
TIB Project Information
City of Gold Bar's 1st Street
6-P-819(004)-1
6-P-819(004)-1
1st Street
SR 2 to May Creek Rd
FY 2021 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $296,137
County: Snohomish | Legislative District: 39 | Project Length: 0.39 | TIB Engineer: Greg Armstrong | Last Payment Date: 12/31/2020
Project Information
Lead Agency | GOLD BAR |
Funding Year | 2021 |
Program | SCAP |
Current Phase | Audit |
Legislative District | 39 |
Congressional District | 1 |
Federal Route Number | 2841 |
Project Length | 0.39 mi. |
ADT | 500 |
Functional Class | Collector |
Type of Work | Reconstruction |
Project Contact | Rich Norris |
Contact Email | r.norris@cityofgoldbar.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | 12/31/2020 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 07/01/2022 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2020 | 12/10/2019 |
Bid Auth. Approval | 06/20/2020 | 06/11/2020 |
Construction Approval | 07/22/2020 | 07/22/2020 |
Project Closeout | 12/31/2020 | 12/31/2020 |
Audit Date | 12/31/2020 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 55,981 | 49,268 |
Right of Way | 0 | 0 |
Total Design | 55,981 | 49,268 |
Construction Engineering | 55,981 | 18,655 |
Construction Contract | 373,208 | 243,708 |
Other Construction | 0 | 0 |
Total Construction | 429,189 | 262,363 |
Funding Surplus | - 189,033 | |
Total TIB Funding | 296,137 | 311,631 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GOLD BAR | 15,494 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 15,494 | 5.0% |
Project Description
Proposed improvements include grinding and overlaying the existing road surface to extend lifespan and provide an improved travel surface. The project will also upgrade ADA crossings as required at impacted intersections.
Existing Condition
Project Benefits
- Extends improvements;
- Restores structural condition
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |