City of Goldendale's Darland Drive Reconstruction

6-E-935(010)-1

6-E-935(010)-1
Darland Drive Reconstruction

Railroad Ave to Mill St

FY 2026 Small City Arterial Program
Current Phase : Bid Authorization
Total TIB Funding : $963,753

County: Klickitat   |   Legislative District: 14   |   Project Length: 0.42   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency GOLDENDALE
Funding Year 2026
Program SCAP
Current Phase Bid Authorization
Legislative District 14
Congressional District 4
Federal Route Number 9999
Project Length 0.42 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Sandy Wells
Contact Email swells@ci.goldendale.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date   04/11/2025
Predesign Approval
Design Approval 12/31/2024 01/07/2025
Bid Auth. Approval 03/04/2025 04/21/2025
Construction Approval 05/15/2025
Project Closeout 08/23/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 93,266 103,629
Right of Way 0 0
Total Design 93,266 103,629
     
Construction Engineering 93,266 103,629
Construction Contract 777,221 863,578
Other Construction 0 0
Total Construction 870,487 967,207
     
Total TIB Funding 963,753 1,070,836

Local Funding Partners

Funding Amount Percent
GOLDENDALE 107,083 10.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 107,083 10.0%

Project Description

Project will add sidewalk and compliant ADA ramps as well as reconstruct the roadway.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments