Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Brewster's Old Hwy 97

6-E-876(I05)-1

6-E-876(I05)-1
Old Hwy 97

US 97 to North C/L

FY 2024 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $166,298

County: Okanogan   |   Legislative District: 12   |   Project Length: 0.46   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 11/14/2024

Project Information

Lead Agency BREWSTER
Funding Year 2024
Program SCAP
Current Phase Audit
Legislative District 12
Congressional District 4
Federal Route Number E241
Project Length 0.46 mi.
ADT 3,106
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Misty Ruiz
Contact Email misty.ruiz@brewsterwa.us
TIB Engineer Andrew Beagle
Last Payment Date 11/14/2024
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date   04/05/2023
Predesign Approval
Design Approval 01/01/2023 12/12/2022
Bid Auth. Approval 03/15/2023 05/09/2023
Construction Approval 05/31/2023 08/15/2023
Project Closeout 12/15/2024 11/08/2024
Audit Date   11/14/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 14,993 146,056
Right of Way 0 0
Total Design 14,993 146,056
     
Construction Engineering 22,559 194,715
Construction Contract 144,968 1,053,930
Other Construction 0 0
Total Construction 167,527 1,248,645
     
Funding Surplus - 16,222  
Total TIB Funding 166,298 1,394,701

Local Funding Partners

Funding Amount Percent
BREWSTER 297 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
Federal Funding  1,228,106 86.5%
Total Local Funding 1,228,403 88.3%

Project Description

Full reconstruction of roadway to include widening for safety shoulders, sight distance correction, striping, guardrail and provide stormwater drainage.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.