Recently constructed housing developments have significantly increased traffic volumes on Apple Avenue and deteriorated the pavement condition.
Projects — TIB Project Information
TIB Project Information
City of Royal City's Apple Avenue Reconstruction
6-E-864(005)-1
6-E-864(005)-1
Apple Avenue Reconstruction
Road 13 SW to Poplar St
FY 2026 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $1,071,220
County: Grant | Legislative District: 13 | Project Length: 0.50 | TIB Engineer: Jonathan Heusman | Last Payment Date:
Project Information
Lead Agency | ROYAL CITY |
Funding Year | 2026 |
Program | SCAP |
Current Phase | Design |
Legislative District | 13 |
Congressional District | 4 |
Federal Route Number | 13AE |
Project Length | 0.50 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Reconstruction |
Project Contact | John Lasen |
Contact Email | rcpw@royalcitywa.org |
TIB Engineer | Jonathan Heusman |
Last Payment Date | |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2025 | 04/07/2025 |
Bid Auth. Approval | 12/01/2025 | |
Construction Approval | 02/01/2026 | |
Project Closeout | 10/01/2026 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 114,000 | 120,000 |
Right of Way | 0 | 0 |
Total Design | 114,000 | 120,000 |
Construction Engineering | 114,000 | 120,000 |
Construction Contract | 843,220 | 887,600 |
Other Construction | 0 | 0 |
Total Construction | 957,220 | 1,007,600 |
Total TIB Funding | 1,071,220 | 1,127,600 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ROYAL CITY | 56,380 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 56,380 | 5.0% |
Project Description
The project will involve reconstructing the roadway, adding curbs to separate the street from the sidewalk, and slightly widening the roadway to better accommodate farm and industrial traffic.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |