Louisiana Ave. PCR 59, 63
Projects — TIB Project Information
TIB Project Information
City of Chehalis's NW Louisiana Ave Overlay
3-W-193(007)-1
3-W-193(007)-1
NW Louisiana Ave Overlay
NW Louisiana Avenue from Chamber of Commerce Way through the roundabout at the southern leg of NW Arkansas Way
FY 2026 Arterial Preservation Program
Current Phase : Design
Total TIB Funding : $808,921
County: Lewis | Legislative District: 20 | Project Length: 0.27 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | CHEHALIS |
Funding Year | 2026 |
Program | APP |
Current Phase | Design |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 5655 |
Project Length | 0.27 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | Celest Wilder |
Contact Email | cwilder@ci.chehalis.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 12/30/2024 | 01/06/2025 |
Bid Auth. Approval | 06/01/2025 | |
Construction Approval | 07/01/2025 | |
Project Closeout | 12/01/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 93,336 | 103,705 |
Right of Way | 0 | 0 |
Total Design | 93,336 | 103,705 |
Construction Engineering | 93,336 | 103,705 |
Construction Contract | 622,249 | 691,380 |
Other Construction | 0 | 0 |
Total Construction | 715,585 | 795,085 |
Total TIB Funding | 808,921 | 898,790 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CHEHALIS | 89,869 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 89,869 | 10.0% |
Project Description
2 inch grind and overlay
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |