City of Port Townsend's Tyler Street Overlay

3-W-151(004)-1

3-W-151(004)-1
Tyler Street Overlay

Jefferson St to Lawrence St

FY 2024 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $303,077

County: Jefferson   |   Legislative District: 24   |   Project Length: 0.24   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 12/11/2024

Project Information

Lead Agency PORT TOWNSEND
Funding Year 2024
Program APP
Current Phase Construction
Legislative District 24
Congressional District 6
Federal Route Number 7604
Project Length 0.24 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Steve King PE
Contact Email sking@cityofpt.us
TIB Engineer Chris Langhoff
Last Payment Date 12/11/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/28/2023 03/30/2023
Bid Auth. Approval 03/30/2025 02/06/2025
Construction Approval 04/30/2025 03/17/2025
Project Closeout 12/01/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 31,605 75,069
Right of Way 0 0
Total Design 31,605 75,069
     
Construction Engineering 31,605 72,468
Construction Contract 316,145 456,635
Other Construction 0 0
Total Construction 347,750 529,103
     
Funding Surplus - 76,278  
Total TIB Funding 303,077 604,172

Local Funding Partners

Funding Amount Percent
PORT TOWNSEND 301,095 49.8%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 301,095 49.8%

Project Description

2 inch overlay

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments