Projects — TIB Project Information
TIB Project Information
City of Sedro Woolley's 2025 Overlay
3-W-126(011)-1
3-W-126(011)-1
2025 Overlay
Multiple Locations
FY 2026 Arterial Preservation Program
Current Phase : Bid Authorization
Total TIB Funding : $737,915
County: Skagit | Legislative District: 39 | Project Length: 0.80 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | SEDRO WOOLLEY |
Funding Year | 2026 |
Program | APP |
Current Phase | Bid Authorization |
Legislative District | 39 |
Congressional District | 2 |
Federal Route Number | 7377 |
Project Length | 0.80 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | William Bullock |
Contact Email | bbullock@sedro-woolley.gov |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2025 | 01/29/2025 |
Bid Auth. Approval | 05/06/2025 | 04/18/2025 |
Construction Approval | 05/28/2025 | |
Project Closeout | 08/29/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 38,675 | 45,500 |
Right of Way | 0 | 0 |
Total Design | 38,675 | 45,500 |
Construction Engineering | 40,375 | 47,500 |
Construction Contract | 658,865 | 775,136 |
Other Construction | 0 | 0 |
Total Construction | 699,240 | 822,636 |
Total TIB Funding | 737,915 | 868,136 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SEDRO WOOLLEY | 130,221 | 15.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 130,221 | 15.0% |
Project Description
2 inch overlay
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |