The pavement condition rating of 276th Street NW - 73rd Ave NW to E C/L is 54.
Projects — TIB Project Information
TIB Project Information
City of Stanwood's FY 2022 Overlay Project
3-P-823(007)-1
3-P-823(007)-1
FY 2022 Overlay Project
Multiple Locations
FY 2022 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $223,021
County: Snohomish | Legislative District: 10 | Project Length: 0.32 | TIB Engineer: Greg Armstrong | Last Payment Date: 08/16/2021
Project Information
| Lead Agency | STANWOOD |
| Funding Year | 2022 |
| Program | APP |
| Current Phase | Audit |
| Legislative District | 10 |
| Congressional District | 2 |
| Federal Route Number | 9304 |
| Project Length | 0.32 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Resurfacing |
| Project Contact | Shawn Smith |
| Contact Email | shawn.smith@ci.stanwood.wa.us |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 08/16/2021 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/20/2020 | |
| Delayed Project Date | 07/01/2023 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2021 | 01/08/2021 |
| Bid Auth. Approval | 04/01/2021 | 03/08/2021 |
| Construction Approval | 04/12/2021 | 04/12/2021 |
| Project Closeout | 08/01/2021 | 07/28/2021 |
| Audit Date | 08/16/2021 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 22,500 | 20,711 |
| Right of Way | 0 | 0 |
| Total Design | 22,500 | 20,711 |
| Construction Engineering | 3,600 | 14,444 |
| Construction Contract | 238,279 | 212,646 |
| Other Construction | 0 | 0 |
| Total Construction | 241,879 | 227,090 |
| Funding Surplus | - 41,358 | |
| Total TIB Funding | 223,021 | 247,801 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| STANWOOD | 24,780 | 10.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 24,780 | 10.0% |
Project Description
The project grinds and provides a 2-inch overlay of 276th Street NW - 73rd Ave NW to E C/L
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||