The pavement condition rating of this segment of 80th Avenue NW is 54.
Projects — TIB Project Information
TIB Project Information
City of Stanwood's 80th Avenue NW Overlay
3-P-823(010)-1
3-P-823(010)-1
80th Avenue NW Overlay
279th Pl NW to 284th St NW
FY 2026 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $133,627
County: Snohomish | Legislative District: 10 | Project Length: 0.29 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | STANWOOD |
Funding Year | 2026 |
Program | APP |
Current Phase | Construction |
Legislative District | 10 |
Congressional District | 2 |
Federal Route Number | 9307 |
Project Length | 0.29 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Alan Lytton |
Contact Email | alan.lytton@ci.stanwood.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2025 | 12/16/2024 |
Bid Auth. Approval | 02/13/2025 | 02/12/2025 |
Construction Approval | 03/27/2025 | 03/31/2025 |
Project Closeout | 07/15/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 23,890 | 13,840 |
Right of Way | 0 | 0 |
Total Design | 23,890 | 13,840 |
Construction Engineering | 7,963 | 9,579 |
Construction Contract | 190,857 | 137,320 |
Other Construction | 0 | 0 |
Total Construction | 198,820 | 146,899 |
Funding Surplus | - 89,083 | |
Total TIB Funding | 133,627 | 160,739 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
STANWOOD | 27,112 | 16.9% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 27,112 | 16.9% |
Project Description
80th Avenue NW - 279th Pl NW to 284th St NW 2-inch grind and overlay
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |