City of Stanwood's 80th Avenue NW Overlay

3-P-823(010)-1

3-P-823(010)-1
80th Avenue NW Overlay

279th Pl NW to 284th St NW

FY 2026 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $133,627

County: Snohomish   |   Legislative District: 10   |   Project Length: 0.29   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency STANWOOD
Funding Year 2026
Program APP
Current Phase Construction
Legislative District 10
Congressional District 2
Federal Route Number 9307
Project Length 0.29 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Alan Lytton
Contact Email alan.lytton@ci.stanwood.wa.us
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2025 12/16/2024
Bid Auth. Approval 02/13/2025 02/12/2025
Construction Approval 03/27/2025 03/31/2025
Project Closeout 07/15/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 23,890 13,840
Right of Way 0 0
Total Design 23,890 13,840
     
Construction Engineering 7,963 9,579
Construction Contract 190,857 137,320
Other Construction 0 0
Total Construction 198,820 146,899
     
Funding Surplus - 89,083  
Total TIB Funding 133,627 160,739

Local Funding Partners

Funding Amount Percent
STANWOOD 27,112 16.9%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 27,112 16.9%

Project Description

80th Avenue NW - 279th Pl NW to 284th St NW 2-inch grind and overlay

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments