City of Brier's 2022 Overlay Award

3-P-144(005)-1

3-P-144(005)-1
2022 Overlay Award

Multiple Locations

FY 2024 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $769,660

County: Snohomish   |   Legislative District: 1   |   Project Length: 0.90   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 10/15/2024

Project Information

Lead Agency BRIER
Funding Year 2024
Program APP
Current Phase Audit
Legislative District 1
Congressional District 2
Federal Route Number 2537
Project Length 0.90 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Steven Smith
Contact Email pwsuper@ci.brier.wa.us
TIB Engineer Greg Armstrong
Last Payment Date 10/15/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 01/25/2023
Bid Auth. Approval 04/01/2024 04/02/2024
Construction Approval 04/23/2024 04/26/2024
Project Closeout 10/31/2024 10/08/2024
Audit Date   10/15/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 89,250 68,387
Right of Way 0 0
Total Design 89,250 68,387
     
Construction Engineering 55,250 34,457
Construction Contract 901,000 802,638
Other Construction 0 0
Total Construction 956,250 837,095
     
Funding Surplus - 275,840  
Total TIB Funding 769,660 905,482

Local Funding Partners

Funding Amount Percent
BRIER 135,822 15.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 135,822 15.0%

Project Description

The project grinds and provides a 2-inch overlay the following segments 214th St SW - Poplar Wy and 36th Ave W - 5 ADA ramps Old Poplar Way - 228th St to Brier Rd - 5 ADA ramps

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments