City of Brier's FY 2021 Overlay Project
3-P-144(004)-1
3-P-144(004)-1
FY 2021 Overlay Project
Multiple Locations
FY 2021 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $229,284
County: Snohomish | Legislative District: 1 | Project Length: 0.58 | TIB Engineer: Greg Armstrong | Last Payment Date: 12/31/2020
Project Information
| Lead Agency | BRIER |
| Funding Year | 2021 |
| Program | APP |
| Current Phase | Audit |
| Legislative District | 1 |
| Congressional District | 2 |
| Federal Route Number | 2524 |
| Project Length | 0.58 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Resurfacing |
| Project Contact | Steve Smith |
| Contact Email | pwsuper@ci.brier.wa.us |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 12/31/2020 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2019 | |
| Delayed Project Date | 07/01/2022 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2020 | 12/16/2019 |
| Bid Auth. Approval | 05/25/2020 | 05/20/2020 |
| Construction Approval | 06/24/2020 | 06/26/2020 |
| Project Closeout | 12/31/2020 | 12/10/2020 |
| Audit Date | 12/31/2020 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 34,675 | 31,285 |
| Right of Way | 0 | 0 |
| Total Design | 34,675 | 31,285 |
| Construction Engineering | 34,674 | 18,212 |
| Construction Contract | 332,868 | 220,249 |
| Other Construction | 0 | 0 |
| Total Construction | 367,542 | 238,461 |
| Funding Surplus | - 172,933 | |
| Total TIB Funding | 229,284 | 269,746 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| BRIER | 40,462 | 15.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 40,462 | 15.0% |
Project Description
This project grinds and provides a 2-inch overlay of the following segments 228th Street SW - Brier Road to East C/L 228th Street SW - West C/L to 38th Pl W
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||