City of Snohomish's FY 2021 Overlay Project
3-P-142(006)-1
3-P-142(006)-1
FY 2021 Overlay Project
Multiple Locations
FY 2021 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $571,149
County: Snohomish | Legislative District: 44 | Project Length: 0.87 | TIB Engineer: Greg Armstrong | Last Payment Date: 02/01/2022
Project Information
Lead Agency | SNOHOMISH |
Funding Year | 2021 |
Program | APP |
Current Phase | Audit |
Legislative District | 44 |
Congressional District | 1 |
Federal Route Number | 2658 |
Project Length | 0.87 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Andrew Sics |
Contact Email | sics@snohomishwa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 02/01/2022 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2019 | |
Delayed Project Date | 07/01/2022 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2020 | 12/13/2019 |
Bid Auth. Approval | 06/10/2021 | 06/09/2021 |
Construction Approval | 07/01/2021 | 07/01/2021 |
Project Closeout | 01/31/2022 | 01/27/2022 |
Audit Date | 02/01/2022 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 29,750 | 0 |
Right of Way | 0 | 0 |
Total Design | 29,750 | 0 |
Construction Engineering | 34,000 | 8,500 |
Construction Contract | 679,915 | 740,649 |
Other Construction | 0 | 0 |
Total Construction | 713,915 | 749,149 |
Funding Increase | 52,958 | |
Funding Surplus | - 225,474 | |
Total TIB Funding | 571,149 | 749,149 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SNOHOMISH | 178,000 | 23.8% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 178,000 | 23.8% |
Project Description
This project will grind and provide a 2-inch overlay of the following segments Park Avenue - Hill Park entrance and North C/L Bickford Avenue - 15th Street roundabout and SR-9 4th Street - Avenue E to Avenue J Avenue D - McDonalds N Property Line to 10th Street City will upgrade ADA at their own costs prior to the project.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |