City of Snohomish's N Bickford Avenue Overlay

3-P-142(011)-1

3-P-142(011)-1
N Bickford Avenue Overlay

3000 Blk to N C/L

FY 2026 Arterial Preservation Program
Current Phase : Design
Total TIB Funding : $963,135

County: Snohomish   |   Legislative District: 44   |   Project Length: 0.69   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency SNOHOMISH
Funding Year 2026
Program APP
Current Phase Design
Legislative District 44
Congressional District 1
Federal Route Number 2628
Project Length 0.69 mi.
ADT 0
Functional Class Minor
Type of Work Resurfacing
Project Contact Cory Morton
Contact Email morton@snohomishwa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/17/2025 01/14/2025
Bid Auth. Approval 03/01/2026
Construction Approval 05/01/2026
Project Closeout 08/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 21,436 30,000
Right of Way 0 0
Total Design 21,436 30,000
     
Construction Engineering 0 0
Construction Contract 941,699 1,317,900
Other Construction 0 0
Total Construction 941,699 1,317,900
     
Total TIB Funding 963,135 1,347,900

Local Funding Partners

Funding Amount Percent
SNOHOMISH 384,765 28.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 384,765 28.5%

Project Description

N Bickford Avenue - 3000 Block to N C/L 2-inch grind and overlay

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.