Projects — TIB Project Information
TIB Project Information
City of Snohomish's FY 2021 Overlay Project
3-P-142(006)-1
3-P-142(006)-1
FY 2021 Overlay Project
Multiple Locations
FY 2021 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $571,149
County: Snohomish | Legislative District: 44 | Project Length: 0.87 | TIB Engineer: Greg Armstrong | Last Payment Date: 02/01/2022
Project Information
| Lead Agency | SNOHOMISH |
| Funding Year | 2021 |
| Program | APP |
| Current Phase | Audit |
| Legislative District | 44 |
| Congressional District | 1 |
| Federal Route Number | 2658 |
| Project Length | 0.87 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Resurfacing |
| Project Contact | Andrew Sics |
| Contact Email | sics@snohomishwa.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 02/01/2022 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2019 | |
| Delayed Project Date | 07/01/2022 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2020 | 12/13/2019 |
| Bid Auth. Approval | 06/10/2021 | 06/09/2021 |
| Construction Approval | 07/01/2021 | 07/01/2021 |
| Project Closeout | 01/31/2022 | 01/27/2022 |
| Audit Date | 02/01/2022 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 29,750 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 29,750 | 0 |
| Construction Engineering | 34,000 | 8,500 |
| Construction Contract | 679,915 | 740,649 |
| Other Construction | 0 | 0 |
| Total Construction | 713,915 | 749,149 |
| Funding Increase | 52,958 | |
| Funding Surplus | - 225,474 | |
| Total TIB Funding | 571,149 | 749,149 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| SNOHOMISH | 178,000 | 23.8% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 178,000 | 23.8% |
Project Description
This project will grind and provide a 2-inch overlay of the following segments Park Avenue - Hill Park entrance and North C/L Bickford Avenue - 15th Street roundabout and SR-9 4th Street - Avenue E to Avenue J Avenue D - McDonalds N Property Line to 10th Street City will upgrade ADA at their own costs prior to the project.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||