City of West Richland's Keene Road Overlay

3-E-172(006)-1

3-E-172(006)-1
Keene Road Overlay

C/L to Bombing Range Rd

FY 2026 Arterial Preservation Program
Current Phase : Design
Total TIB Funding : $400,000

County: Benton   |   Legislative District: 16   |   Project Length: 0.69   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency WEST RICHLAND
Funding Year 2026
Program APP
Current Phase Design
Legislative District 16
Congressional District 4
Federal Route Number 3435
Project Length 0.69 mi.
ADT 0
Functional Class Minor
Type of Work Resurfacing
Project Contact Julie R West
Contact Email jwest@westrichland.org
TIB Engineer Jonathan Heusman
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 06/30/2025 01/07/2025
Bid Auth. Approval 02/08/2026
Construction Approval 06/03/2026
Project Closeout 12/04/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 26,181 49,000
Right of Way 0 0
Total Design 26,181 49,000
     
Construction Engineering 16,029 30,000
Construction Contract 357,790 669,638
Other Construction 0 0
Total Construction 373,819 699,638
     
Total TIB Funding 400,000 748,638

Local Funding Partners

Funding Amount Percent
WEST RICHLAND 348,638 46.6%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 348,638 46.6%

Project Description

2-inch grind and overlay, paint line

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.