City of Pullman's Orchard Drive Overlay

3-E-167(005)-1

3-E-167(005)-1
Orchard Drive Overlay

From Orchard and Stadium Way northeast along Orchard to Valley then west along Valley to Cove Way

FY 2026 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $314,084

County: Whitman   |   Legislative District: 9   |   Project Length: 0.48   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 03/18/2025

Project Information

Lead Agency PULLMAN
Funding Year 2026
Program APP
Current Phase Construction
Legislative District 9
Congressional District 5
Federal Route Number 7410
Project Length 0.48 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Cara Haley
Contact Email cara.haley@pullman-wa.gov
TIB Engineer Jonathan Heusman
Last Payment Date 03/18/2025
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/16/2025 12/09/2024
Bid Auth. Approval 02/17/2025 02/12/2025
Construction Approval 04/02/2025 03/18/2025
Project Closeout 10/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 6,599 8,000
Right of Way 0 0
Total Design 6,599 8,000
     
Construction Engineering 14,848 24,000
Construction Contract 327,218 365,295
Other Construction 0 0
Total Construction 342,066 389,295
     
Funding Surplus - 34,581  
Total TIB Funding 314,084 397,295

Local Funding Partners

Funding Amount Percent
PULLMAN 83,211 20.9%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 83,211 20.9%

Project Description

2' grind and overlay. ADA ramp upgrades.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments