Existing roadway is in need of rehabilitation.
Projects — TIB Project Information
TIB Project Information
City of Pullman's Orchard Drive Overlay
3-E-167(005)-1
3-E-167(005)-1
Orchard Drive Overlay
From Orchard and Stadium Way northeast along Orchard to Valley then west along Valley to Cove Way
FY 2026 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $314,084
County: Whitman | Legislative District: 9 | Project Length: 0.48 | TIB Engineer: Jonathan Heusman | Last Payment Date: 03/18/2025
Project Information
Lead Agency | PULLMAN |
Funding Year | 2026 |
Program | APP |
Current Phase | Construction |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 7410 |
Project Length | 0.48 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Cara Haley |
Contact Email | cara.haley@pullman-wa.gov |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 03/18/2025 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/16/2025 | 12/09/2024 |
Bid Auth. Approval | 02/17/2025 | 02/12/2025 |
Construction Approval | 04/02/2025 | 03/18/2025 |
Project Closeout | 10/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 6,599 | 8,000 |
Right of Way | 0 | 0 |
Total Design | 6,599 | 8,000 |
Construction Engineering | 14,848 | 24,000 |
Construction Contract | 327,218 | 365,295 |
Other Construction | 0 | 0 |
Total Construction | 342,066 | 389,295 |
Funding Surplus | - 34,581 | |
Total TIB Funding | 314,084 | 397,295 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
PULLMAN | 83,211 | 20.9% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 83,211 | 20.9% |
Project Description
2' grind and overlay. ADA ramp upgrades.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |