Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of East Wenatchee's Valley Mall Parkway Overlay

3-E-161(005)-1

3-E-161(005)-1
Valley Mall Parkway Overlay

Multiple Locations

FY 2026 Arterial Preservation Program
Current Phase : Design
Total TIB Funding : $665,767

County: Douglas   |   Legislative District: 12   |   Project Length: 0.36   |   TIB Engineer: Andrew Beagle   |   Last Payment Date:

Project Information

Lead Agency EAST WENATCHEE
Funding Year 2026
Program APP
Current Phase Design
Legislative District 12
Congressional District 4
Federal Route Number 5901
Project Length 0.36 mi.
ADT 0
Functional Class Minor
Type of Work Resurfacing
Project Contact Garren Melton
Contact Email gmelton@eastwenatcheewa.gov
TIB Engineer Andrew Beagle
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2025 01/08/2025
Bid Auth. Approval 04/25/2025
Construction Approval 06/03/2025
Project Closeout 10/01/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 56,421 66,378
Right of Way 0 0
Total Design 56,421 66,378
     
Construction Engineering 45,137 53,102
Construction Contract 564,209 663,775
Other Construction 0 0
Total Construction 609,346 716,877
     
Total TIB Funding 665,767 783,255

Local Funding Partners

Funding Amount Percent
EAST WENATCHEE 117,488 15.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 117,488 15.0%

Project Description

Grind and overlay full width of roadway, perform pavement repair as needed.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments