Many of our streets have the potential to be seal coated with chip seal for preservation, but there are portions of these streets that need significant pre-level work with HMA. The HMA pre-level work should be done at least year prior to the seal coat because fresh HMA tends to adsorb the oil to quickly, which results in poor adherence of the rock chips.
Projects — TIB Project Information
TIB Project Information
City of Montesano's 2025 Maintenance Project
2-W-957(017)-1
2-W-957(017)-1
2025 Maintenance Project
Multiple Locations
FY 2026 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $96,425
County: Grays Harbor | Legislative District: 24 | Project Length: 0.00 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | MONTESANO |
Funding Year | 2026 |
Program | SCPP |
Current Phase | Construction |
Legislative District | 24 |
Congressional District | 6 |
Federal Route Number | 9999 |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Mike Olden |
Contact Email | molden@montesano.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2025 | 12/18/2024 |
Bid Auth. Approval | 05/01/2025 | 03/06/2025 |
Construction Approval | 05/15/2025 | 03/28/2025 |
Project Closeout | 07/15/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 123,500 | 101,500 |
Other Construction | 0 | 0 |
Total Construction | 123,500 | 101,500 |
Funding Surplus | - 27,075 | |
Total TIB Funding | 96,425 | 101,500 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MONTESANO | 5,075 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 5,075 | 5.0% |
Project Description
Current City priorities for future pre-level work are on Arland, Simpson (E. W.), E. Elma and W. Marcy Avenues.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |