City of Everson's 2025 Otta Seal

2-W-838(005)-1

2-W-838(005)-1
2025 Otta Seal

Approximately Meade Ave to Everson Rd and Washington St. to Shuksan Way

FY 2026 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $1,448,196

County: Whatcom   |   Legislative District: 42   |   Project Length: 0.78   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency EVERSON
Funding Year 2026
Program SCPP
Current Phase Design
Legislative District 42
Congressional District 2
Federal Route Number 9999
Project Length 0.78 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Dave Schoonover
Contact Email dschoonover@thecityofeverson.com
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2025 12/16/2024
Bid Auth. Approval 05/07/2025
Construction Approval 06/10/2025
Project Closeout 09/30/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 120,681 127,033
Right of Way 0 0
Total Design 120,681 127,033
     
Construction Engineering 120,681 127,033
Construction Contract 1,206,834 1,270,352
Other Construction 0 0
Total Construction 1,327,515 1,397,385
     
Total TIB Funding 1,448,196 1,524,418

Local Funding Partners

Funding Amount Percent
EVERSON 76,222 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 76,222 5.0%

Project Description

Pulverize and otta seal

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.