Several Streets in the City are beginning to show signs (cracks) of needing to be resurfaced soon.
Projects — TIB Project Information
TIB Project Information
City of Granite Falls's 2025 Crack Seal
2-P-820(010)-1
2-P-820(010)-1
2025 Crack Seal
Multiple Locations
FY 2026 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $35,513
County: Snohomish | Legislative District: 39 | Project Length: 0.00 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | GRANITE FALLS |
Funding Year | 2026 |
Program | SCPP |
Current Phase | Construction |
Legislative District | 39 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Brent Kirk |
Contact Email | brent.kirk@ci.granite-falls.wa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2025 | 12/05/2024 |
Bid Auth. Approval | 02/01/2025 | 02/07/2025 |
Construction Approval | 02/28/2025 | 02/20/2025 |
Project Closeout | 06/30/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 62,100 | 39,459 |
Other Construction | 0 | 0 |
Total Construction | 62,100 | 39,459 |
Funding Surplus | - 26,587 | |
Total TIB Funding | 35,513 | 39,459 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GRANITE FALLS | 3,946 | 10.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 3,946 | 10.0% |
Project Description
Perform a City-wide crack seal project. This work will be the first crack seal phase to crack seal all streets in Granite Falls that have TIB PCRs between 45 and 80.
Existing Condition
Project Benefits
- Fills Cracks
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |