City of Granite Falls's Alpine Street Overlay
2-P-820(009)-1
2-P-820(009)-1
Alpine Street Overlay
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $199,922
County: Snohomish | Legislative District: 39 | Project Length: 0.25 | TIB Engineer: Greg Armstrong | Last Payment Date: 10/31/2024
Project Information
| Lead Agency | GRANITE FALLS |
| Funding Year | 2025 |
| Program | SCPP |
| Current Phase | Audit |
| Legislative District | 39 |
| Congressional District | 8 |
| Federal Route Number | 9999 |
| Project Length | 0.25 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Brent Kirk |
| Contact Email | brent.kirk@ci.granite-falls.wa.us |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 10/31/2024 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/01/2024 | 12/07/2023 |
| Bid Auth. Approval | 05/10/2024 | 05/06/2024 |
| Construction Approval | 05/29/2024 | 05/31/2024 |
| Project Closeout | 10/31/2024 | 10/29/2024 |
| Audit Date | 10/31/2024 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 18,651 | 10,000 |
| Right of Way | 0 | 0 |
| Total Design | 18,651 | 10,000 |
| Construction Engineering | 13,322 | 5,000 |
| Construction Contract | 200,627 | 210,106 |
| Other Construction | 0 | 0 |
| Total Construction | 213,949 | 215,106 |
| Funding Surplus | - 32,678 | |
| Total TIB Funding | 199,922 | 225,106 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| GRANITE FALLS | 25,184 | 11.2% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 25,184 | 11.2% |
Project Description
2-inch overlay, edge grind and pavement repair of the following segments E Alpine Street - N Indiana Ave to N Alder Ave E Alpine Street - 400ft e/o N Granite Ave to N Indiana Ave W Alpine Street - Hemming Way and N Granite Ave
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||