The pavement condition rating of Elk Loop is 68.
Projects — TIB Project Information
TIB Project Information
Town of Carbonado's Elk Loop Overlay
2-P-809(004)-1
2-P-809(004)-1
Elk Loop Overlay
9th St NW to 9th St NW
FY 2026 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $140,805
County: Pierce | Legislative District: 31 | Project Length: 0.17 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | CARBONADO |
Funding Year | 2026 |
Program | SCPP |
Current Phase | Construction |
Legislative District | 31 |
Congressional District | 8 |
Federal Route Number | 9999 |
Project Length | 0.17 mi. |
ADT | 0 |
Functional Class | |
Type of Work | |
Project Contact | Sandi Carlson |
Contact Email | sandicarlson@carbonado.org |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/31/2025 | 12/11/2024 |
Bid Auth. Approval | 05/01/2025 | 03/19/2025 |
Construction Approval | 04/09/2025 | 04/15/2025 |
Project Closeout | 10/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 23,000 | 23,000 |
Right of Way | 0 | 0 |
Total Design | 23,000 | 23,000 |
Construction Engineering | 23,000 | 9,500 |
Construction Contract | 191,400 | 108,305 |
Other Construction | 0 | 0 |
Total Construction | 214,400 | 117,805 |
Funding Surplus | - 96,595 | |
Total TIB Funding | 140,805 | 140,805 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CARBONADO | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Elk Loop - 9th Street NW to 9th Street NW 2-inch overlay and pavement repair
Existing Condition
Project Benefits
- The pavement condition rating of Elk Loop is 68.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |