City of Wapato's 2024 Otta Seal
2-E-946(004)-1
2-E-946(004)-1
2024 Otta Seal
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Closeout
Total TIB Funding : $620,229
County: Yakima | Legislative District: 15 | Project Length: 5.00 | TIB Engineer: Jonathan Heusman | Last Payment Date: 01/08/2025
Project Information
Lead Agency | WAPATO |
Funding Year | 2025 |
Program | SCPP |
Current Phase | Closeout |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 5.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Jeff Schumacker |
Contact Email | jschumacker@wapato-city.org |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 01/08/2025 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 10/12/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 10/20/2023 | 11/02/2023 |
Bid Auth. Approval | 12/31/2023 | 03/21/2024 |
Construction Approval | 04/30/2024 | 04/24/2024 |
Project Closeout | 12/31/2024 | 04/08/2025 |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 23,750 | 29,480 |
Right of Way | 0 | 0 |
Total Design | 23,750 | 29,480 |
Construction Engineering | 120,745 | 36,735 |
Construction Contract | 805,505 | 569,571 |
Other Construction | 0 | 17,087 |
Total Construction | 926,250 | 623,393 |
Funding Surplus | - 329,771 | |
Total TIB Funding | 620,229 | 652,873 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
WAPATO | 32,644 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 32,644 | 5.0% |
Project Description
To perform an Otta Seal on several streets throughout the town.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |