City of White Salmon's Dock Grade Road Chip Seal

2-E-936(007)-1

2-E-936(007)-1
Dock Grade Road Chip Seal

SR14 to SR141

FY 2026 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $146,430

County: Klickitat   |   Legislative District: 14   |   Project Length: 0.83   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency WHITE SALMON
Funding Year 2026
Program SCPP
Current Phase Design
Legislative District 14
Congressional District 4
Federal Route Number 9999
Project Length 0.83 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Andrew Dirks
Contact Email andrew@ci.white-salmon.wa.us
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2025 01/29/2025
Bid Auth. Approval 07/01/2025
Construction Approval 07/01/2025
Project Closeout 11/15/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 146,430 154,137
Other Construction 0 0
Total Construction 146,430 154,137
     
Total TIB Funding 146,430 154,137

Local Funding Partners

Funding Amount Percent
WHITE SALMON 7,707 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 7,707 5.0%

Project Description

Chip seal

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.