City of Bingen's City of Bingen 2025 Overlay
2-E-934(003)-1
2-E-934(003)-1
City of Bingen 2025 Overlay
Multiple Locations
FY 2026 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $278,827
County: Klickitat | Legislative District: 14 | Project Length: 0.16 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | BINGEN |
Funding Year | 2026 |
Program | SCPP |
Current Phase | Design |
Legislative District | 14 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.16 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Krista Loney |
Contact Email | administrator@bingenwashington.org |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2025 | 12/03/2024 |
Bid Auth. Approval | 07/15/2025 | |
Construction Approval | 07/15/2025 | |
Project Closeout | 10/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 1,900 | 2,000 |
Construction Contract | 276,927 | 291,502 |
Other Construction | 0 | 0 |
Total Construction | 278,827 | 293,502 |
Total TIB Funding | 278,827 | 293,502 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
BINGEN | 14,675 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 14,675 | 5.0% |
Project Description
2 inch overlay
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |