Town of Endicott's 2025 Scrub Seal

2-E-909(004)-1

2-E-909(004)-1
2025 Scrub Seal

Multiple Locations

FY 2026 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $277,317

County: Whitman   |   Legislative District: 9   |   Project Length: 1.21   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency ENDICOTT
Funding Year 2026
Program SCPP
Current Phase Design
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 1.21 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Kim Zolman
Contact Email townofendicott@gmail.com
TIB Engineer Jonathan Heusman
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/03/2025 03/27/2025
Bid Auth. Approval 05/01/2025
Construction Approval 06/16/2025
Project Closeout 01/01/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 22,745 22,745
Right of Way 0 0
Total Design 22,745 22,745
     
Construction Engineering 22,745 22,745
Construction Contract 231,827 231,827
Other Construction 0 0
Total Construction 254,572 254,572
     
Total TIB Funding 277,317 277,317

Local Funding Partners

Funding Amount Percent
ENDICOTT 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Scrub Seal

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.