Town of Northport's 2025 Street Maintenance
2-E-905(004)-1
2-E-905(004)-1
2025 Street Maintenance
Multiple Locations
FY 2026 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $280,500
County: Stevens | Legislative District: 7 | Project Length: 0.00 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
Lead Agency | NORTHPORT |
Funding Year | 2026 |
Program | SCPP |
Current Phase | Design |
Legislative District | 7 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 0.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Karen Baribault |
Contact Email | townofnorthport@outlook.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 12/15/2024 | 12/03/2024 |
Bid Auth. Approval | 05/01/2025 | |
Construction Approval | 07/01/2025 | |
Project Closeout | 09/30/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 280,500 | 280,500 |
Other Construction | 0 | 0 |
Total Construction | 280,500 | 280,500 |
Total TIB Funding | 280,500 | 280,500 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
NORTHPORT | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Pavement repair and/or overlay patches throughout the network. Additional maintenance solutions may be evaluated and proposed after the 2024-2025 snow season should additional distresses be identified prior to 2025 Construction Season.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |