Most of Iones streets are in good to fair condition where crack sealing and pavement repair will be the least expensive fix to increase the PCR. Approximately 2.0 miles of streets meet this category. About 0.25 miles of streets in Ione have a PCR rating below 50.
Projects — TIB Project Information
TIB Project Information
Town of Ione's 2025 Street Maintenance
2-E-889(008)-1
2-E-889(008)-1
2025 Street Maintenance
City Wide Multiple Locations
FY 2026 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $250,000
County: Pend Oreille | Legislative District: 7 | Project Length: 1.50 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
Lead Agency | IONE |
Funding Year | 2026 |
Program | SCPP |
Current Phase | Design |
Legislative District | 7 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 1.50 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | John Cannon |
Contact Email | townclerk@potc.net |
TIB Engineer | Andrew Beagle |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2025 | 12/05/2024 |
Bid Auth. Approval | 05/25/2025 | |
Construction Approval | 06/15/2025 | |
Project Closeout | 10/30/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 250,000 | 250,000 |
Other Construction | 0 | 0 |
Total Construction | 250,000 | 250,000 |
Total TIB Funding | 250,000 | 250,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
IONE | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Crack sealing and pavement repair of alligator cracking in 2025. The next treatment would be a city wide chip seal in 2026.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |