Town roads throughout Cusick have cracking distresses
Projects — TIB Project Information
TIB Project Information
Town of Cusick's 2025 Street Maintenance
2-E-888(004)-1
2-E-888(004)-1
2025 Street Maintenance
Multiple Locations
FY 2026 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $122,939
County: Pend Oreille | Legislative District: 7 | Project Length: 3.20 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
Lead Agency | CUSICK |
Funding Year | 2026 |
Program | SCPP |
Current Phase | Design |
Legislative District | 7 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 3.20 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | |
Project Contact | Julie SiJohn |
Contact Email | clerk@townofcusick.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2024 | |
Delayed Project Date | 07/01/2027 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2025 | 01/27/2025 |
Bid Auth. Approval | 05/25/2025 | |
Construction Approval | 06/15/2025 | |
Project Closeout | 10/30/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 122,939 | 122,939 |
Other Construction | 0 | 0 |
Total Construction | 122,939 | 122,939 |
Total TIB Funding | 122,939 | 122,939 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
CUSICK | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Town-wide crack seal project to prepare the roads for chip sealing the same in the next 2-4 years.
Existing Condition
Project Benefits
- Extend asset life-cycle.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |