 Projects — TIB Project Information

TIB Project Information

City of Pateros's 2025 Chip Seal

2-E-883(009)-1

2-E-883(009)-1
2025 Chip Seal

Multiple Locations

FY 2026 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $343,064

County: Okanogan   |   Legislative District: 7   |   Project Length: 1.01   |   TIB Engineer: Andrew Beagle   |   Last Payment Date:

Project Information

Lead Agency PATEROS
Funding Year 2026
Program SCPP
Current Phase Design
Legislative District 7
Congressional District 4
Federal Route Number 9999
Project Length 1.01 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Jord Wilson
Contact Email jwilson@pateros.us
TIB Engineer Andrew Beagle
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 12/01/2024 12/19/2024
Bid Auth. Approval 05/01/2025
Construction Approval 06/02/2025
Project Closeout 09/29/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 15,593 15,593
Right of Way 0 0
Total Design 15,593 15,593
     
Construction Engineering 15,593 15,593
Construction Contract 311,878 311,878
Other Construction 0 0
Total Construction 327,471 327,471
     
Total TIB Funding 343,064 343,064

Local Funding Partners

Funding Amount Percent
PATEROS 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Chip Seal.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments