Town of Rainier's FY 2021 Overlay Project

2-W-976(002)-1

2-W-976(002)-1
FY 2021 Overlay Project

Multiple Locations

FY 2021 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $136,602

County: Thurston   |   Legislative District: 2   |   Project Length: 0.23   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 04/15/2022

Project Information

Lead Agency RAINIER
Funding Year 2021
Program SCPP
Current Phase Audit
Legislative District 2
Congressional District 10
Federal Route Number K341
Project Length 0.23 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Charmanye Garrison
Contact Email rainier@ywave.com
TIB Engineer Chris Langhoff
Last Payment Date 04/15/2022

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2019
Delayed Project Date 07/01/2022  
Predesign Approval
Design Approval 02/01/2020 01/21/2020
Bid Auth. Approval 04/15/2021 04/19/2021
Construction Approval 05/15/2021 05/25/2021
Project Closeout 03/31/2022 04/07/2022
Audit Date   04/15/2022
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 18,340 21,893
Right of Way 0 0
Total Design 18,340 21,893
     
Construction Engineering 18,340 20,475
Construction Contract 122,273 117,990
Other Construction 0 0
Total Construction 140,613 138,465
     
Funding Increase 16,890  
Funding Surplus - 39,241  
Total TIB Funding 136,602 160,358

Local Funding Partners

Funding Amount Percent
RAINIER 23,756 14.8%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 23,756 14.8%

Project Description

The work will include overlaying of Rainier Road from 505 Minnesota Street west to the City limits. This project, if funded, will include the dig out and subgrade repair of the areas showing severe alligator cracking. Traffic will be diverted around the project area using 133rd Ave SE to Centre Street as a bypass during construction. This will allow continuous traffic flow to the City and construction work to proceed uninterrupted.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.