Projects — TIB Project Information
TIB Project Information
Town of Rainier's FY 2018 Rehabilitation Project
2-W-976(001)-1
2-W-976(001)-1
FY 2018 Rehabilitation Project
Multiple Locations
FY 2018 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $222,310
County: Thurston | Legislative District: 2 | Project Length: 3.09 | TIB Engineer: Chris Langhoff | Last Payment Date: 05/31/2018
Project Information
Lead Agency | RAINIER |
Funding Year | 2018 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 2 |
Congressional District | 10 |
Federal Route Number | 9999 |
Project Length | 3.09 mi. |
ADT | 150 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Charmayne Garrison |
Contact Email | rainier@ywave.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 05/31/2018 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/18/2016 | |
Delayed Project Date | 07/01/2019 | |
Predesign Approval | ||
Design Approval | 01/01/2017 | 12/16/2016 |
Bid Auth. Approval | 04/01/2017 | 06/01/2017 |
Construction Approval | 05/01/2017 | 06/01/2017 |
Project Closeout | 10/31/2017 | 05/23/2018 |
Audit Date | 05/31/2018 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 10,500 | 10,500 |
Right of Way | 0 | 0 |
Total Design | 10,500 | 10,500 |
Construction Engineering | 0 | 6,500 |
Construction Contract | 214,500 | 399,613 |
Other Construction | 0 | 9,333 |
Total Construction | 214,500 | 415,446 |
Funding Surplus | - 2,690 | |
Total TIB Funding | 222,310 | 425,946 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
RAINIER | 203,636 | 47.8% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 203,636 | 47.8% |
Project Description
Thurston County will FDR the existing roadway and place HMA over the re-graded roadway.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |