Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Stevenson's FY 2020 Seal Coat Project

2-W-974(001)-1

2-W-974(001)-1
FY 2020 Seal Coat Project

Multiple Locations

FY 2020 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $23,763

County: Skamania   |   Legislative District: 14   |   Project Length: 0.75   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 10/31/2019

Project Information

Lead Agency STEVENSON
Funding Year 2020
Program SCPP
Current Phase Audit
Legislative District 14
Congressional District 3
Federal Route Number 9999
Project Length 0.75 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Karl Russell
Contact Email karl@ci.stevenson.wa.us
TIB Engineer Chris Langhoff
Last Payment Date 10/31/2019

Project Schedule

  Target Date Actual Date
Project Selection Date   11/16/2018
Delayed Project Date 07/01/2021  
Predesign Approval
Design Approval 01/01/2019 12/04/2018
Bid Auth. Approval 05/01/2019 12/04/2018
Construction Approval 06/01/2019 12/04/2018
Project Closeout 12/31/2019 10/28/2019
Audit Date   10/31/2019
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 40,815 25,014
Other Construction 0 0
Total Construction 40,815 25,014
     
Funding Surplus - 17,052  
Total TIB Funding 23,763 25,014

Local Funding Partners

Funding Amount Percent
STEVENSON 1,251 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,251 5.0%

Project Description

Chip Seal, Pavement Repair, Sweeping and Traffic Control

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments