T he PCR score is 36 which is within the optium range for an overlay.
Projects — TIB Project Information
TIB Project Information
City of South Bend's FY 2012 Overlay Project
2-W-972(003)-1
2-W-972(003)-1
FY 2012 Overlay Project
Multiple Locations
FY 2012 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $87,204
County: Pacific | Legislative District: 19 | Project Length: 0.24 | TIB Engineer: Chris Langhoff | Last Payment Date: 02/24/2012
Project Information
Lead Agency | SOUTH BEND |
Funding Year | 2012 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 19 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.24 mi. |
ADT | 150 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Steve Russell |
Contact Email | sbcity@sou thbend-wa.gov |
TIB Engineer | Chris Langhoff |
Last Payment Date | 02/24/2012 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2010 | |
Delayed Project Date | 07/01/2013 | |
Predesign Approval | ||
Design Approval | 12/15/2010 | 12/17/2010 |
Bid Auth. Approval | 03/01/2012 | 12/17/2010 |
Construction Approval | 04/01/2012 | 07/19/2011 |
Project Closeout | 03/31/2012 | 02/16/2012 |
Audit Date | 02/24/2012 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 3,670 | 6,793 |
Right of Way | 0 | 0 |
Total Design | 3,670 | 6,793 |
Construction Engineering | 3,670 | 6,115 |
Construction Contract | 53,835 | 73,918 |
Other Construction | 0 | 378 |
Total Construction | 57,505 | 80,411 |
Funding Increase | 28,328 | |
Funding Surplus | - 2,299 | |
Total TIB Funding | 87,204 | 87,204 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SOUTH BEND | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will repair areas of base failure with digouts and overlay Harrison Street between SR 101 and Raymond/South Bend Road with a 2-inch overlay.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |