Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of South Bend's Seal Coat Project

2-W-972(001)-1

2-W-972(001)-1
Seal Coat Project

City of South Bend

FY 2007 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $60,844

County: Pacific   |   Legislative District: 19   |   Project Length: 4,850.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 09/13/2006

Project Information

Lead Agency SOUTH BEND
Funding Year 2007
Program SCPP
Current Phase Audit
Legislative District 19
Congressional District 3
Federal Route Number 9999
Project Length 4850.00 mi.
ADT 150
Functional Class Collector
Type of Work Resurfacing
Project Contact Karl Heinicke, Mayor
Contact Email
TIB Engineer Chris Langhoff
Last Payment Date 09/13/2006

Project Schedule

  Target Date Actual Date
Project Selection Date   01/27/2006
Delayed Project Date 07/01/2008  
Predesign Approval
Design Approval 01/27/2006
Bid Auth. Approval 01/27/2006 01/27/2006
Construction Approval 07/01/2006 05/15/2006
Project Closeout 10/31/2006 09/26/2006
Audit Date   09/13/2006
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 57,070 60,844
Other Construction 0 0
Total Construction 57,070 60,844
     
Funding Increase 3,774  
Total TIB Funding 60,844 60,844

Local Funding Partners

Funding Amount Percent
SOUTH BEND 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Small City Preservation Seal Coat Project Water Street - SR-101 to Monroe Street Central Avenue - First Avenue to Fourth Avenue Pacific Avenue - First Avenue to Fifth Avenue

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.