City of South Bend's Seal Coat Project
2-W-972(001)-1
2-W-972(001)-1
Seal Coat Project
City of South Bend
FY 2007 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $60,844
County: Pacific | Legislative District: 19 | Project Length: 4,850.00 | TIB Engineer: Chris Langhoff | Last Payment Date: 09/13/2006
Project Information
Lead Agency | SOUTH BEND |
Funding Year | 2007 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 19 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 4850.00 mi. |
ADT | 150 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Karl Heinicke, Mayor |
Contact Email | |
TIB Engineer | Chris Langhoff |
Last Payment Date | 09/13/2006 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 01/27/2006 | |
Delayed Project Date | 07/01/2008 | |
Predesign Approval | ||
Design Approval | 01/27/2006 | |
Bid Auth. Approval | 01/27/2006 | 01/27/2006 |
Construction Approval | 07/01/2006 | 05/15/2006 |
Project Closeout | 10/31/2006 | 09/26/2006 |
Audit Date | 09/13/2006 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 57,070 | 60,844 |
Other Construction | 0 | 0 |
Total Construction | 57,070 | 60,844 |
Funding Increase | 3,774 | |
Total TIB Funding | 60,844 | 60,844 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SOUTH BEND | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Small City Preservation Seal Coat Project Water Street - SR-101 to Monroe Street Central Avenue - First Avenue to Fourth Avenue Pacific Avenue - First Avenue to Fifth Avenue
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |