Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Raymond's 2024 Red Town Initiative

2-W-971(003)-1

2-W-971(003)-1
2024 Red Town Initiative

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Bid Authorization
Total TIB Funding : $1,520,000

County: Pacific   |   Legislative District: 19   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 04/05/2024

Project Information

Lead Agency RAYMOND
Funding Year 2025
Program SCPP
Current Phase Bid Authorization
Legislative District 19
Congressional District 3
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Mark Burrus
Contact Email mburrus@hwlochner.com
TIB Engineer Chris Langhoff
Last Payment Date 04/05/2024

Project Schedule

  Target Date Actual Date
Project Selection Date   10/17/2023
Delayed Project Date 07/01/2026  
Predesign Approval
Design Approval 10/31/2023 10/19/2023
Bid Auth. Approval 05/01/2024 04/16/2024
Construction Approval 05/31/2024
Project Closeout 10/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 23,750 25,000
Right of Way 0 0
Total Design 23,750 25,000
     
Construction Engineering 166,250 175,000
Construction Contract 1,330,000 1,400,000
Other Construction 0 0
Total Construction 1,496,250 1,575,000
     
Total TIB Funding 1,520,000 1,600,000

Local Funding Partners

Funding Amount Percent
RAYMOND 80,000 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 80,000 5.0%

Project Description

To identify the best candidate streets in the City to perform an Otta Seal or Scrub Seal on and develop basic plans and specs for soliciting bids.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments