Projects — TIB Project Information
TIB Project Information
City of Toledo's 2017 Emergency Pavement Repair Project
2-W-965(003)-1
2-W-965(003)-1
2017 Emergency Pavement Repair Project
Various Locations
FY 2017 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $10,581
County: Lewis | Legislative District: 20 | Project Length: 0.10 | TIB Engineer: Chris Langhoff | Last Payment Date: 09/15/2017
Project Information
Lead Agency | TOLEDO |
Funding Year | 2017 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Craig McCown |
Contact Email | wwtp@toledotel.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 09/15/2017 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 05/11/2017 | |
Delayed Project Date | 07/01/2019 | |
Predesign Approval | ||
Design Approval | 06/10/2017 | 05/22/2017 |
Bid Auth. Approval | 06/10/2017 | 05/22/2017 |
Construction Approval | 06/10/2017 | 05/22/2017 |
Project Closeout | 08/31/2017 | 09/13/2017 |
Audit Date | 09/15/2017 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 23,580 | 10,581 |
Other Construction | 0 | 0 |
Total Construction | 23,580 | 10,581 |
Funding Surplus | - 12,999 | |
Total TIB Funding | 10,581 | 10,581 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
TOLEDO | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
See approved repair list.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |