Projects — TIB Project Information
TIB Project Information
Town of Pe Ell's FY 2015 Overlay Project
2-W-964(002)-1
2-W-964(002)-1
FY 2015 Overlay Project
Multiple Locations
FY 2015 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $219,227
County: Lewis | Legislative District: 20 | Project Length: 0.28 | TIB Engineer: Chris Langhoff | Last Payment Date: 05/01/2015
Project Information
Lead Agency | PE ELL |
Funding Year | 2015 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.28 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Jeanette Schwartz |
Contact Email | peellclerk@centurytel.net |
TIB Engineer | Chris Langhoff |
Last Payment Date | 05/01/2015 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/22/2013 | |
Delayed Project Date | 07/01/2016 | |
Predesign Approval | ||
Design Approval | 01/01/2014 | 01/07/2014 |
Bid Auth. Approval | 07/01/2014 | 06/23/2014 |
Construction Approval | 07/15/2014 | 07/22/2014 |
Project Closeout | 01/31/2015 | 04/21/2015 |
Audit Date | 05/01/2015 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 23,205 | 23,205 |
Right of Way | 0 | 0 |
Total Design | 23,205 | 23,205 |
Construction Engineering | 23,205 | 24,230 |
Construction Contract | 154,700 | 201,792 |
Other Construction | 0 | 0 |
Total Construction | 177,905 | 226,022 |
Funding Increase | 26,210 | |
Funding Surplus | - 8,089 | |
Total TIB Funding | 219,227 | 249,227 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
PE ELL | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Weyerhauser | 30,000 | 11.7% |
Total Local Funding | 30,000 | 11.7% |
Project Description
This project repairs failed areas of pavement and places a two-inch asphalt overlay on 3rd Street from Pleasant Avenue to the South City Limits. This is an arterial route that gets extremely heavy truck traffic from Weyerhauser. This will complete improvements along 3rd Street from SR 6 to the City Limits.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |