The PCR ratings for the selected segments are as follows Alder Street - Pe Ell Ave to Omer St 52 Maple Street - Pe Ell Ave to Omer St 20 Omer Street - Alder St to Maple St 28
Projects — TIB Project Information
TIB Project Information
Town of Pe Ell's FY 2014 Seal Coat Project
2-W-964(001)-1
2-W-964(001)-1
FY 2014 Seal Coat Project
Multiple Locations
FY 2014 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $46,749
County: Lewis | Legislative District: 20 | Project Length: 0.34 | TIB Engineer: Chris Langhoff | Last Payment Date: 05/29/2013
Project Information
Lead Agency | PE ELL |
Funding Year | 2014 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.34 mi. |
ADT | 0 |
Functional Class | Local Access |
Type of Work | Resurfacing |
Project Contact | Pat Gill |
Contact Email | pgill@g-o.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 05/29/2013 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2012 | |
Delayed Project Date | 07/01/2015 | |
Predesign Approval | ||
Design Approval | 01/01/2013 | 12/05/2012 |
Bid Auth. Approval | 06/01/2013 | 12/05/2012 |
Construction Approval | 07/01/2013 | 03/19/2013 |
Project Closeout | 06/01/2013 | 05/20/2013 |
Audit Date | 05/29/2013 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 2,033 | 0 |
Right of Way | 0 | 0 |
Total Design | 2,033 | 0 |
Construction Engineering | 2,033 | 0 |
Construction Contract | 42,683 | 47,927 |
Other Construction | 0 | 0 |
Total Construction | 44,716 | 47,927 |
Total TIB Funding | 46,749 | 47,927 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
PE ELL | 1,178 | 2.5% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 1,178 | 2.5% |
Project Description
This project will prelevel and chip seal 3 continuous streets in Pe Ell.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |