Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Mossyrock's 2023 Lewis and Thurston Bundle

2-W-962(006)-1

2-W-962(006)-1
2023 Lewis and Thurston Bundle

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $263,000

County: Lewis   |   Legislative District: 20   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 01/31/2024

Project Information

Lead Agency MOSSYROCK
Funding Year 2025
Program SCPP
Current Phase Audit
Legislative District 20
Congressional District 3
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact
Contact Email
TIB Engineer Chris Langhoff
Last Payment Date 01/31/2024

Project Schedule

  Target Date Actual Date
Project Selection Date   04/03/2023
Delayed Project Date 07/01/2025  
Predesign Approval
Design Approval 04/15/2023 04/18/2023
Bid Auth. Approval 04/15/2023 04/24/2023
Construction Approval 05/15/2023 05/26/2023
Project Closeout 02/28/2024 01/24/2024
Audit Date   01/31/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 2,845 4,031
Right of Way 0 0
Total Design 2,845 4,031
     
Construction Engineering 5,689 7,705
Construction Contract 205,000 251,264
Other Construction 0 0
Total Construction 210,689 258,969
     
Funding Increase 63,963  
Funding Surplus - 14,497  
Total TIB Funding 263,000 263,000

Local Funding Partners

Funding Amount Percent
MOSSYROCK 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Chip seal, scrub seal and crack seal

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments