City of Mossyrock's FY 2012 Overlay Project
2-W-962(001)-1
2-W-962(001)-1
FY 2012 Overlay Project
Multiple Locations
FY 2012 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $63,554
County: Lewis | Legislative District: 20 | Project Length: 0.24 | TIB Engineer: Chris Langhoff | Last Payment Date: 12/06/2012
Project Information
Lead Agency | MOSSYROCK |
Funding Year | 2012 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.24 mi. |
ADT | 175 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Tom Meade |
Contact Email | cityofmossyrock@tds.net |
TIB Engineer | Chris Langhoff |
Last Payment Date | 12/06/2012 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2010 | |
Delayed Project Date | 07/01/2013 | |
Predesign Approval | ||
Design Approval | 03/01/2011 | 02/23/2011 |
Bid Auth. Approval | 03/01/2012 | 02/23/2011 |
Construction Approval | 04/30/2012 | 05/22/2012 |
Project Closeout | 12/30/2012 | 12/03/2012 |
Audit Date | 12/06/2012 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 3,612 | 0 |
Right of Way | 0 | 0 |
Total Design | 3,612 | 0 |
Construction Engineering | 3,612 | 0 |
Construction Contract | 52,964 | 30,889 |
Other Construction | 0 | 32,665 |
Total Construction | 56,576 | 63,554 |
Funding Increase | 13,868 | |
Funding Surplus | - 10,502 | |
Total TIB Funding | 63,554 | 63,554 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MOSSYROCK | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
This project will overlay Godfrey Road between State Street and the south city limit with a 2-inch overlay.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |