TIB Project Information

City of Morton's 2024 Red Town Initiative

2-W-961(006)-1

2-W-961(006)-1
2024 Red Town Initiative

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $1,092,500

County: Lewis   |   Legislative District: 20   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency MORTON
Funding Year 2025
Program SCPP
Current Phase Design
Legislative District 20
Congressional District 3
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Mike Meskimen
Contact Email mmeskimen@g-o.com
TIB Engineer Chris Langhoff
Last Payment Date

Project Schedule

  Target Date Actual Date
Project Selection Date   10/13/2023
Delayed Project Date 07/01/2026  
Predesign Approval
Design Approval 10/31/2023 11/02/2023
Bid Auth. Approval 05/01/2024
Construction Approval 06/01/2024
Project Closeout 10/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 23,750 25,000
Right of Way 0 0
Total Design 23,750 25,000
     
Construction Engineering 23,750 25,000
Construction Contract 1,045,000 1,100,000
Other Construction 0 0
Total Construction 1,068,750 1,125,000
     
Total TIB Funding 1,092,500 1,150,000

Local Funding Partners

Funding Amount Percent
MORTON 57,500 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 57,500 5.0%

Project Description

To identify the best candidate streets in the City to perform an Otta Seal or Scrub Seal on and develop basic plans and specs for soliciting bids.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.