The PCR ratings for the selected segments are as follows Airport Way - Westlake Ave to end 50 Westlake Avenue - 2nd to Knittles Way 60
Projects — TIB Project Information
TIB Project Information
City of Morton's FY 2014 Red Town Project
2-W-961(003)-1
2-W-961(003)-1
FY 2014 Red Town Project
Multiple Locations
FY 2014 Small City Preservation Program
Current Phase : Withdrawn
Total TIB Funding : $0
County: Lewis | Legislative District: 20 | Project Length: 0.49 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | MORTON |
Funding Year | 2014 |
Program | SCPP |
Current Phase | Withdrawn |
Legislative District | 20 |
Congressional District | 0 |
Federal Route Number | 9999 |
Project Length | 0.49 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Mayor James Gerwig |
Contact Email | |
TIB Engineer | Chris Langhoff |
Last Payment Date |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2012 | |
Delayed Project Date | 07/01/2015 | |
Predesign Approval | ||
Design Approval | 01/01/2013 | 01/28/2013 |
Bid Auth. Approval | 07/01/2013 | 06/24/2013 |
Construction Approval | 03/01/2014 | |
Project Closeout | 12/30/2014 | |
Audit Date | ||
Withdrawn Date | 01/07/2014 |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 0 | 0 |
Other Construction | 0 | 0 |
Total Construction | 0 | 0 |
Total TIB Funding | 0 | 0 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MORTON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 6.4% |
Project Description
This project will grind and overlay Westlake Avenue from 2nd Street to Knittles Way and Airport Road from Westlake Avenue to the east end. This project will also grind the existing pavement on Adams Street, place a 1-inch asphalt prelevel and a 2-inch asphalt wearing course. The City is providing an additional $11,000 for utility work that will be completed in conjunction with the Adams Street work. Westlake Avenue from 2nd Street to Knittles Way and Airport Way from Westlake Avenue to the east end will also be overlayed with a 2-inch wearing course. All sidewalk ramps within the project limits will be upgraded to current standards.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |