TIB Project Information

City of Oakville's Maintenance Crack Seal

2-W-958(003)-1

2-W-958(003)-1
Maintenance Crack Seal

City Wide

FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $71,500

County: Grays Harbor   |   Legislative District: 19   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 11/01/2022

Project Information

Lead Agency OAKVILLE
Funding Year 2023
Program SCPP
Current Phase Audit
Legislative District 19
Congressional District 6
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Richard Armstrong
Contact Email oakvillepublicworks@gmail.com
TIB Engineer Chris Langhoff
Last Payment Date 11/01/2022

Project Schedule

  Target Date Actual Date
Project Selection Date   07/11/2022
Delayed Project Date 07/01/2025  
Predesign Approval
Design Approval 08/01/2022 07/28/2022
Bid Auth. Approval 08/01/2022 07/28/2022
Construction Approval 08/01/2022 07/28/2022
Project Closeout 10/01/2022 10/21/2022
Audit Date   11/01/2022
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 71,500 71,500
Other Construction 0 0
Total Construction 71,500 71,500
     
Total TIB Funding 71,500 71,500

Local Funding Partners

Funding Amount Percent
OAKVILLE 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Maintenance crack seal

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments