City of Montesano's E Pioneer Avenue Overlay

2-W-957(007)-1

2-W-957(007)-1
E Pioneer Avenue Overlay

Academy St to Glenn St

FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $106,444

County: Grays Harbor   |   Legislative District: 19   |   Project Length: 0.19   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 07/05/2022

Project Information

Lead Agency MONTESANO
Funding Year 2023
Program SCPP
Current Phase Audit
Legislative District 19
Congressional District 6
Federal Route Number 9999
Project Length 0.19 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Mike Olden
Contact Email molden@montesano.us
TIB Engineer Chris Langhoff
Last Payment Date 07/05/2022

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
Predesign Approval
Design Approval 02/01/2022 12/17/2021
Bid Auth. Approval 05/01/2022 02/14/2022
Construction Approval 05/15/2022 03/03/2022
Project Closeout 08/15/2022 06/16/2022
Audit Date   07/05/2022
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 110,000 135,475
Other Construction 0 0
Total Construction 110,000 135,475
     
Funding Increase 530  
Funding Surplus - 4,086  
Total TIB Funding 106,444 135,475

Local Funding Partners

Funding Amount Percent
MONTESANO 29,031 21.4%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 29,031 21.4%

Project Description

Grind/Mill old existing pavement to 1-inch depth, to 1 from edge of existing pavement. Install overlay with 2-inch depth at centerline crown out to match 1-inch depth at edge to match existing. Pre-level as needed prior to final HMA course. Stripe.