Many of our streets have the potential to be seal coated with chip seal for preservation, but there are portions of these streets that need significant pre-level work. The HMA prelevel work should be done the year prior to the seal coat because fresh HMA tends to adsorb the oil to quickly, which results in poor adherance of the rock.
Projects — TIB Project Information
TIB Project Information
City of Montesano's 2021 Small City Maintenance
2-W-957(009)-1
2-W-957(009)-1
2021 Small City Maintenance
Multiple Locations
FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $47,288
County: Grays Harbor | Legislative District: 24 | Project Length: 0.10 | TIB Engineer: Chris Langhoff | Last Payment Date: 08/31/2022
Project Information
Lead Agency | MONTESANO |
Funding Year | 2023 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 24 |
Congressional District | 6 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Mike Olden |
Contact Email | molden@montesano.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 08/31/2022 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/29/2021 | |
Delayed Project Date | 07/01/2024 | |
Predesign Approval | ||
Design Approval | 02/01/2022 | 12/20/2021 |
Bid Auth. Approval | 05/15/2022 | 12/20/2021 |
Construction Approval | 06/01/2022 | 12/20/2021 |
Project Closeout | 10/01/2022 | 08/25/2022 |
Audit Date | 08/31/2022 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 50,000 | 49,936 |
Other Construction | 0 | 0 |
Total Construction | 50,000 | 49,936 |
Funding Surplus | - 2,712 | |
Total TIB Funding | 47,288 | 49,936 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MONTESANO | 2,648 | 5.3% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 2,648 | 5.3% |
Project Description
Prelevel streets at least one year in advance of a seal coat (chip seal) project. This upcoming year, the City would prelevel Arland Avenue so that we could submit a chip seal project for funding in 2023. The cost per ton shown below is based on previous experience and includes a provision for rising costs and contingencies to make sure that we can prelevel what we need to prelevel.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |