 Projects — TIB Project Information

TIB Project Information

City of McCleary's 2023 Seal Coat Award

2-W-956(005)-1

2-W-956(005)-1
2023 Seal Coat Award

Multiple Locations

FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $87,424

County: Grays Harbor   |   Legislative District: 19   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 12/14/2023

Project Information

Lead Agency MCCLEARY
Funding Year 2024
Program SCPP
Current Phase Audit
Legislative District 19
Congressional District 6
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Chad Bedlington
Contact Email chadb@cityofmccleary.com
TIB Engineer Chris Langhoff
Last Payment Date 12/14/2023

Project Schedule

  Target Date Actual Date
Project Selection Date   03/24/2023
Delayed Project Date 07/01/2025  
Predesign Approval
Design Approval 04/30/2023 05/29/2023
Bid Auth. Approval 06/15/2023 05/29/2023
Construction Approval 07/01/2023 08/07/2023
Project Closeout 10/30/2023 12/04/2023
Audit Date   12/14/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 100,000 69,526
Other Construction 0 22,499
Total Construction 100,000 92,025
     
Funding Surplus - 12,576  
Total TIB Funding 87,424 92,025

Local Funding Partners

Funding Amount Percent
MCCLEARY 4,601 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 4,601 5.0%

Project Description

Chip seal

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments