TIB Project Information

Town of Yacolt's Maintenance Crack Seal

2-W-951(007)-1

2-W-951(007)-1
Maintenance Crack Seal

FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $56,225

County: Clark   |   Legislative District: 19   |   Project Length: 0.10   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 01/03/2023

Project Information

Lead Agency YACOLT
Funding Year 2023
Program SCPP
Current Phase Audit
Legislative District 19
Congressional District 0
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact
Contact Email
TIB Engineer Chris Langhoff
Last Payment Date 01/03/2023

Project Schedule

  Target Date Actual Date
Project Selection Date   06/14/2022
Delayed Project Date 07/01/2024  
Predesign Approval
Design Approval 07/15/2022 07/07/2022
Bid Auth. Approval 07/15/2022 07/07/2022
Construction Approval 07/15/2022 07/07/2022
Project Closeout 11/30/2022 12/20/2022
Audit Date   01/03/2023
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 56,225 59,184
Other Construction 0 0
Total Construction 56,225 59,184
     
Total TIB Funding 56,225 59,184

Local Funding Partners

Funding Amount Percent
YACOLT 2,959 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 2,959 5.0%

Project Description

Maintenance crack seal

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments